Project Description

Project Mangement including Drawings and engage Certifier on behalf of the Customer

Demolition of Partitions and removal from site in preparation for workstations

Convert an existing Storage area into a New disabled Toilet as required by CDC

Relocation of a whole floor of Old workstations from a different site approximately about 30kms – Dissassemble, re locate to the new site and re assemble (After Hours)

Build a custom Bulkhead to facilitate lower air conidtioning ducts

Re install Power and Data to newly relocated workstations

Facilitate Fire Design and modifications

Make good all walls and Paint

Complete OC & Handover Documentation

Case Details

Address
32 Phillip St, Parramatta
What We Did
Full Demolition and Make Good

Resources Used

Demolition Team

Electrical Team

Plastering Team

Labour & Truck Team

Plumbing Team

Painting Team